GPI Digital Transformation Program Implementation Roadmap 2027

From Pilot to Institutionalization. The year 2027 takes the GPIBK Synod and the GPIBT Synod from production platforms already up and running to a trusted, everyday way of working, while making the General Synod of GPI a Facilitative Hub that truly functions. Four other synods join as pilots: GMIBM, GPIB, GPID and GERMITA.

Project Plan & GanttStatus: proposal for the BPH of the General Synod of GPIPrepared November 1, 2026 · updated November 17, 2026
2 + 4GPIBK & GPIBT rollout · 4 pilot synods
6Program workstreams
5 · 16Objectives · Key Results
Jun 30Gate G2: production go-live
01

Executive Summary

2027 is the year "From Pilot to Institutionalization": the Digital Transformation Program of the General Synod of GPI takes GPIBK and GPIBT from production platforms already up and running to a trusted, everyday way of working, while making the General Synod a Facilitative Hub that truly functions. This is the second year of the SMSA 2025 Jakarta mandate and the heart of Horizon 2 of the 2025–2030 Strategic Plan.

The starting position as of November 1, 2026 is strong enough to move forward: ±20 active ecosystem platforms, a 16-topic Digital Literacy curriculum and KATEKISASI.ONLINE already live, and the production platforms GPIBK.CHURCH (3,949 active members, 97% already with a membership number) and GPIBT.CHURCH (1,516 active members, 93% numbered) already populated. The weaknesses are just as clear: the data has not been verified, there is no approved data governance yet, and members cannot yet be reached: only 24% of GPIBK members and about 3% of GPIBT members can be phoned, directly or through their family card.

Five outcomes pursued in 2027:

  1. GPIBK & GPIBT production go-live by the end of Q2 2027, starting from pilot classes and then expanding in stages.
  2. The Facilitative Hub is operating: the PMO runs on a quarterly review rhythm and the service catalog for Programs 01–04 is ready to be offered to wave-2 GBM, first tested through four pilots: GMIBM, GPIB, GPID and GERMITA.
  3. Ministers' capacity is built through the GPI Academy tracks: data managers, system administrators, digital leadership, digital literacy for members, and catechism teachers.
  4. Trust and governance: the Digital Ministry and Data Protection Policy (PDP Law No. 27/2022) is approved, and a federated data model is agreed.
  5. Evidence and sustainability: a measurement baseline, the actual cost (TCO) per GBM, and the 2028 funding scheme are agreed.

Decisions requested from the BPH of the General Synod before January 2027: appointment of the Program Sponsor and the PMO, approval of the Project Charter for the GPIBK & GPIBT rollout and the four GBM pilots, appointment of a Project Owner in both synods, and approval of the phase 1 budget (Q1–Q2 2027).

02

Foundation of the Mandate

Every 2027 initiative must be traceable to the Strategic Objectives of SMSA 2025 Jakarta (December 2–5, 2025, theme "Test all things; hold fast what is good", 1 Thessalonians 5:21). The SMSA sharpened the four Pillars of SSA 2025 in Beo, Talaud, into four Strategic Objectives with Key Results.

SMSA 2025 Strategic ObjectivesRelevant Key ResultsTranslated in 2027 into
SS01 — The General Synod as a Facilitation Center (Facilitative Hub)KR 1.1 document on role, functions, and implications for structure/personnel/budget; KR 1.2 three flagship initiatives: Think-and-Do Tank, Koinonia-Diakonia Action Network, Digital Transformation EnablerPMO and Digital Enablement Office operating; service catalog; GBM rollout as a service
SS02 — Leadership competencies & theological capacity in the digital eraKR 2.1 5–7 new competencies (facilitator, content curator, network-weaver); KR 2.2 Theology of Disruption & Digital Ethics curriculum frameworkGPI Academy tracks; competency assessment of GPIBK & GPIBT ministers
SS03 — Strategic pillars and OKRs 2025–2030KR 3.2 at least one complete OKR per pillar2027 program OKRs and an OKR dashboard per GBM
SS04 — A contextual and transformative mission directionKR 4.2 draft pan-GPI Transformative Diakonia pilotLimited digital diakonia pilots (BakuBantu, EcoJustice, youth initiatives)

The Program Proposition of Quarter I 2026 has already cascaded this mandate into four service menus that form the rollout framework: Program 01 Agile Strategic Plan Facilitation, Program 02 Digital Leadership Capacity, Program 03 Transformative Mission & Diakonia, and Program 04 Digital Platform Workshop & Development. This roadmap uses the same five service-flow stages (Design → Offering → Mobilization → Execution → Evaluation) and the five Driving Commissions (Research, PMO, Public Relations, Theology, Financial Self-Reliance).

Three Strategic Plan targets fall squarely in 2027 and need to be monitored from January: the catechism curriculum adopted by at least 10 of 12 GBM in Q2 2027 (KR 1.1.2); 100% of GBM publishing audited financial reports starting in 2027 (KR 3.2.1); and integrated congregation and financial information systems reaching 60% of congregations by 2030 (KR 3.2.2).

03

Baseline as of November 5, 2026

The platform assets already exceed 2027 needs; what lags behind is verified data, governance, and working habits. The focus of 2027 is therefore adoption and institutionalization, not adding more applications.

AreaCurrent conditionGap for 2027
Information hubGEREJABERSAUDARA.ID moved to the pengelola server on October 29, 2026; it hosts the Strategic Plan, the Proposition, toolkits, whitepapers, the forest and land fire map, and the congregation mapNo public dashboard yet for program progress and OKRs
Ecosystem±20 platforms: Sidang, Rapat, Pemilihan, Renungan, Katekisasi, Kolaborasi.Digital, BakuBantu, EcoJustice, Naik.Center, 5 GPIBT youth appsPlatforms do not yet have a service owner, operating costs, or continue/stop criteria
Learning16 Digital Literacy courses (T01–T16); KATEKISASI.ONLINE live since November 1, 2026 (8 stages, 41 lessons)Participant completion and change in skills not yet measured
GPIBKOnline workshops; training in Klasis Salakan & Klasis Peling Timur; production platform GPIBK.CHURCH: 3,949 active members in 39 of 162 congregations, 41 pastors, 659 family cards; Membership Numbers issued November 5 for 3,824 members; 23 congregation websitesData not yet verified by the Church Council; only 24% of members can be phoned; 0 worship records; Membership Number format not yet approved by the MPHS
GPIBT6-day training, September 2026; production platform GPIBT.CHURCH: 1,516 active members in 32 of 43 congregations, 41 pastors, 78 family cards; Membership Numbers for 1,404 members; ±15 congregation websitesOnly 49 members linked to family cards and about 3% can be phoned; data entry stopped after the training; the data structure needs tidying
Governance & dataPrinciples already formulated in the Digital Ecclesiology Whitepaper (review on October 16, 2026)Policy, data processing agreements, and accountable roles not yet approved
MeasurementBSC framework in the Strategic Plan; initial indicators in the whitepaperNo baseline yet; targets cannot yet be locked

Membership figures are read directly from the production databases of GPIBK.CHURCH (November 5, 2026) and GPIBT.CHURCH (November 3–5, 2026). These figures are system records, not the number of members already verified by the Church Council. The November 1 version of this page used a demo copy that turned out to be no longer updated; its figures have been replaced.

Outcomes of the GPIBT (November 3) and GPIBK (November 5, 2026) Evaluation Meetings

Both synods evaluated the program using the same framework, starting from Andi Widjajanto's question ahead of SMSA GPI 2026: if worship and offerings are the first pillar, what is the second pillar of GPI's vitality? The proposed answer is the capacity to bear one another's burdens (the whitepaper The Church at a Turning Point: From Census to Mutual Care). Their shared finding: we know who our members are, but we cannot yet reach them.

Joint proposalContent
Primary measurePercentage of member households that can be reached within 48 hours (becomes KR1.4)
Minimum Pastoral DataFive required fields per household: contact channel, household members, livelihood, vulnerabilities, skills; other fields are no longer completeness targets
Ministry nodesOne operator per congregation and one elder per kolom (neighborhood group) holding the household list, including a printed list
90-day planFamily Card and Contact Channel Month (November 16 – December 15, 2026), attendance register starting the First Sunday of Advent, reports on the 5th of every month, a one-page Data & AI Policy, a tabletop simulation of the 48-Hour Protocol at the end of January 2027
Specific to GPIBKApproval of the Membership Number format (November 16), report to the GPIBK Synod Council Session (November 17–19), pilot classes Salakan and Peling Timur
Specific to GPIBTTidying the data structure, six pilot congregations, accompaniment of MUPEL 4 Galang

Follow-up details are recorded as tasks in the program's Project Plan, and for GPIBK also in the Project Plan "RTL 90 Hari Transformasi Digital GPIBK" on GPIBK.CHURCH.

04

2027 Theme and Design Principles

Theme: "From Pilot to Institutionalization — Facilitated, Not Commanded." By the end of 2027, two GBM run their administrative ministry on production platforms with data they trust, and the General Synod has a proven rollout pattern to offer to other GBM.

Seven principles bind all program decisions:

  1. Subsidiarity. The General Synod does only what the GBM cannot effectively do on their own: standards, shared platforms, learning across GBM.
  2. Ministry needs first, applications second. Every feature is linked to one ministry process and one service owner.
  3. Data remains the GBM's own. A federated model: the General Synod receives aggregates, not all personal records.
  4. Staged, with gates. Expansion only after gate conditions are met; postponing is a legitimate decision.
  5. Phones and weak networks as the design standard. Lightweight, downloadable materials, with local companions.
  6. Theological review before launch. The Theology Commission is the gate for formation materials and for features that touch pastoral space.
  7. Measure activities, abilities, and benefits separately. Targets are locked after the baseline, not before.
05

Program Architecture: Six Workstreams

The 2027 program runs in six workstreams; WS3 (GBM rollout) is the main beneficiary, while the other five provide foundations that are reused for the next GBM.

WorkstreamPillar / SSProposed leadMain 2027 outcomes
WS1 Governance, Policy & DataPillars 3, 4 / SS01PMO + Theology CommissionDigital Ministry & Data Protection Policy; General Synod–GBM data processing agreements; minimum data standards; metadata standardization across platforms
WS2 Shared Platform & IntegrationPillar 4 / SS01Digital Enablement OfficeGBM platform template (SMJ, basic finance, eLearning, congregation websites); Sidang/Rapat/Pemilihan integration; security and recovery baseline
WS3 GBM Rollout (GPIBK, GPIBT) and four pilotsPillars 3, 4 / SS01, SS03PMO + GBM Project OwnerTwo production platforms; pilot classes, then expansion; GBM OKR dashboard; four GBM pilots (GMIBM, GPIB, GPID, GERMITA)
WS4 Capacity & GPI AcademyPillars 1, 3 / SS02Theology Commission + ResearchFive learning tracks; Theology of Disruption & Digital Ethics curriculum; adoption of Katekisasi.Online
WS5 Digital Diakonia & Public WitnessPillar 2 / SS04Research + Financial Self-RelianceLimited BakuBantu pilot; governance of the 5 youth apps; EcoJustice and forest and land fire monitoring as material for local action
WS6 Measurement, Evaluation & SustainabilityPillars 3, 4 / SS03Research + Financial Self-RelianceBaseline survey; program BSC; standardized performance KPIs for each platform; TCO per GBM; 2028 funding scheme

WS1 and WS2 must be completed first for the items that gate go-live; WS4–WS6 run in parallel throughout the year.

06

Digital Transformation Program OKRs 2027

Five Objectives, 16 Key Results. The figures below are proposed targets; the PMO locks them at the first QPR (end of March 2027) once the baseline is available.

ObjectiveKey ResultDeadlineOwner
O1 — GPIBK & GPIBT serve from production platformsKR1.1 Two production platforms pass the go-live gateQ2PMO
KR1.2 ≥90% of congregation Branches in pilot classes have member data verified by the Church Council; sample audit ≥95% accurateQ3GBM Project Owner
KR1.3 Correspondence and office archives of both synods processed digitally (100% of outgoing letters numbered by the system)Q4Synod secretariat
KR1.4 ≥80% of households in pilot classes/congregations can be reached within 48 hours, tested by simulation; starting point measured in January 2027Q2GBM Project Owner
O2 — The General Synod works as a Facilitative HubKR2.1 The PMO holds 4 QPRs and 12 Program Board meetingsQ4Program Sponsor
KR2.2 Service catalog for Programs 01–04 published; ≥2 wave-2 GBM sign an NDA/MoUQ4Public Relations Commission
KR2.3 GPIBK & GPIBT satisfaction index with the General Synod's facilitation ≥4.0 out of 5Q4Research
O3 — Ministers are equipped to lead digital ministryKR3.1 Every pilot classis has ≥2 data managers and 1 certified administratorQ2GPI Academy
KR3.2 Theology of Disruption & Digital Ethics framework approved by the Theology Commission and published as a moduleQ2Theology Commission
KR3.3 Katekisasi.Online used in ≥5 congregations per synod; profiles of the 5–7 ministerial competencies mapped in both synodsQ3GPI Academy
O4 — Members can trust the way the church manages dataKR4.1 Digital Ministry & Data Protection Policy approved by the BPHQ1WS1
KR4.2 Data processing agreements signed with GPIBK & GPIBT before gate G1 (member data is already on the production platforms)Q1WS1
KR4.3 Backup restore tests succeed in 4 of 4 quarters; MFA active for 100% of admin accountsQ4WS2
O5 — 2028 decisions are based on evidenceKR5.1 Baseline survey of members' digital habits completed in both synods, including non-usersQ2Research
KR5.2 Actual cost (TCO) per GBM and per service documentedQ3PMO + Financial Self-Reliance
KR5.3 2028 program budget and list of wave-2 GBM agreed in the Synodal Partnership CouncilQ4Program Sponsor

Strategic Plan KR 1.1.2 (catechism in 10 of 12 GBM by Q2 2027) is at risk of not being met. The proposal: change the target to "available and offered to 12 GBM, adopted in GPIBK & GPIBT", then discuss it at the Q1 QPR.

07

Quarterly Roadmap 2027

Q1 prepares policy, data and the production environment; Q2 is go-live; Q3 expands; Q4 institutionalizes and decides on 2028. The GPIBK and GPIBT rollout lanes and the four pilots are shown in the accent color.

GPIBK and GPIBT live in production by the end of June; expansion completed in October; four GBM pilots January – November
Month
JanFebMarAprMayJunJulAugSepOctNovDec
Gates
G0Jan 8G1Mar 31G2Jun 30G3Oct 29G4Dec 10
WS1 Governance & data
PDP Policy, DPAMinimum data standards
WS2 Shared platform
Production & templatesSidang, Rapat, Pemilihan integration
GPIBK Rollout
F0F1 DataF2 Go-liveF3 ExpansionF4 Self-reliant
GPIBT Rollout
F0F1 DataF2 Go-liveF3 ExpansionF4 Self-reliant
GMIBM Pilot
P0 PreparationP1 AccompanimentP2 Evaluation
GPIB Pilot
P0 PreparationP1 AccompanimentP2 Evaluation
GPID Pilot
P0 PreparationP1 AccompanimentP2 Evaluation
GERMITA Pilot
P0 PreparationP1 AccompanimentP2 Evaluation
WS4 GPI Academy
Data managers & adminsLeadership & catechism
WS5 Digital diakonia
Youth app governanceBakuBantu pilot
WS6 Measurement
Baseline surveyTCO & impact evaluation

The GPIBK and GPIBT rollout lanes and the four pilots are shown in the accent color. Gate G2 (June 30) is the production go-live point.

Conditions for each gate, decided by the Steering Committee (G0, G4) or by the Chair of the GBM Synod together with the PMO (G1–G3):

  1. G0 Kick-off — Charter, Program Sponsor, Project Owner and phase 1 budget approved.
  2. G1 Production-ready (data & processes) — PDP policy approved, data agreements signed, readiness test and recovery drill passed, the five Minimum Pastoral Data fields filled in at the pilots, security baseline met.
  3. G2 Production go-live — pilot classes/congregations working in production; high-priority incidents resolved; phase 2 budget approved based on actual costs.
  4. G3 Expansion completed — all classes live; data quality ≥95%; SOPs available.
  5. G4 2028 Decision — annual evaluation accepted; wave-2 GBM and the 2028 budget agreed in the Synodal Partnership Council.
08

Project Plan and Gantt

This roadmap is run as the GPI Digital Transformation Program 2027 project in the Project app of the TRANSFORMASI.DIGITAL platform. That project is the living schedule: status, owners, and date changes are recorded there. This page is its summary.

13Work lanes (kanban column = Gantt row)
6Milestones: D0 and G0–G4
189Dated tasks, including 121 subtasks; 7 already completed
77Dependencies between tasks

The 90-day follow-up plans of GPIBK and GPIBT are drawn up on each synod's own platform and synchronized automatically to this project every hour. Each of the four GBM pilots has its own lane: WS3 Pilot GMIBM, GPIB, GPID and GERMITA. Figures as of November 17, 2026.

Open Project Plan

View the web GanttEdit in Oiko GANTTTask board by workstreamProject portal for GBM teams
  1. The web Gantt is for signed-in internal users only: a read-only living schedule, with Week, Month, Quarter, or whole-project scales, plus the details of every task.
  2. Oiko GANTT for internal users who edit the schedule: drag bars, change dates, link dependencies, and assign owners directly in the Gantt.
  3. The task board shows a column per workstream. Work status is recorded through the task status, not by moving columns.
  4. The project portal for the GPIBK and GPIBT teams invited as portal users.
MilestoneDeadlineDecided by
D0 BPH DecisionDecember 15, 2026BPH of the General Synod of GPI
G0 Kick-offJanuary 8, 2027Steering Committee
G1 Production-ready (data & processes)March 31, 2027Chair of the GBM Synod together with the PMO
G2 Production go-liveJune 30, 2027Chair of the GBM Synod together with the PMO
G3 Expansion completedOctober 29, 2027Chair of the GBM Synod together with the PMO
G4 2028 DecisionDecember 10, 2027Steering Committee

The web Gantt is open only to signed-in internal users; other visitors are sent to the login page. Oiko GANTT and the task board require an internal account with access to the Project app. The project portal is open only to portal users invited to the project.

09

GPIBK Synod Rollout Project (Banggai Kepulauan)

Goal: GPIBK links its Agile Strategic Plan, congregation data, and leadership in one production platform at GPIBK.CHURCH, live for the pilot classes in June 2027 and for all classes in October 2027. The ministry direction held to: Worship → Discipleship → Fellowship → Ministry → Mission.

Scope: Program 04 (platform) as the backbone, with Program 01 (Agile Strategic Plan + GPIBK OKRs) and Program 02 (digital leadership) built on top of it. Pilot classes: Klasis Salakan and Klasis Peling Timur, which have already taken part in the training.

PhaseTimingMain tasksConditions to proceed
F0 MobilizationJan 2027Project Charter, MoU/NDA, data processing agreement; Project Owner, Data Steward and Liaison Officer appointedCharter signed by the Chair of the GPIBK Synod
F1 Data & ProcessesFeb–MarCleaning and verification of ±3,950 records in GPIBK.CHURCH together with the Church Council; family cards and contact channels; mapping of 5 core processes (membership & attestation, sacraments, pastor placement, basic finance, correspondence); production configuration; readiness test and recovery drillReadiness test passed; data dictionary and Minimum Pastoral Data agreed
F2 Pilot go-liveApr–JunGo-live in 2 pilot classes; 6 weeks of intensive accompaniment; task-based training; Rapat.Online for inter-island coordinationHigh-priority incidents resolved; pilot users complete tasks without assistance
F3 ExpansionJul–OctOther classes in waves; synod finances; GPIBK OKR dashboard; Katekisasi.Online in congregationsData quality ≥95% in classes already live
F4 InstitutionalizationNov–DecHandover to the synod team; SOPs and operations manual; evaluation; 2028 planThe GPIBK team runs daily operations independently

Key indicators: number of Branches with verified data, percentage of administrative transactions recorded in the system, turnaround time for letters/attestations, module completion by data managers, and user satisfaction. The public congregation map continues to show aggregates only.

10

GPIBT Synod Rollout Project (Buol Tolitoli)

Objective: GPIBT turns the results of the 6-day training (September 2026) into daily work habits: automated administration on GPIBT.CHURCH, live for the pilot congregations in May 2027 and for the entire service area in October 2027. GPIBT's distinctive strength is its youth; they are involved as Digital Ambassadors, not merely as users.

Scope: Program 04 (platform & administration) and Program 02 (digital literacy for ministers, staff and congregations) as the core; Program 03 through the governance of five applications built by the youth. The Evaluation Meeting of November 3, 2026 proposed six pilot congregations: Imanuel Centrum, Paulus–Dinopi, Tiberias–Sidoarjo, Maranatha–Malosong, Moria–Bukaan and Nazareth–Harmoni.

PhaseTimingMain tasksConditions to proceed
F0 MobilizationJan 2027Project Charter, MoU/NDA, data processing agreement; Project Owner and Data Steward appointed; youth Digital Ambassador team formedCharter signed by the Chair of the GPIBT Synod
F1 Data & ProcessesJan–MarCompleting member data (1,516 records as of November 5, 2026) and family cards with a focus on Minimum Pastoral Data; mapping the processes for welcoming members, sacraments, correspondence and basic finance; production configurationCore data of pilot congregations complete; readiness test passed
F2 Pilot go-liveApr–MayGo-live in pilot congregations; 6 weeks of intensive mentoring; before/after measurement for one processProcesses running; data managers' workload is reasonable
F3 ExpansionJun–OctOther congregations in waves; ±15 congregation websites maintained from the platform; governance of Ceritain (moderation, referrals), Berkatin (complaints, payments), TalentCall (profile privacy)User complaints resolved; moderation guidelines approved
F4 InstitutionalizationNov–DecHandover to the synod team; SOPs; evaluation; 2028 planThe GPIBT team runs daily operations independently

Difference from GPIBK: GPIBT starts from lower data coverage, so F1 begins earlier and is more intensive. On the other hand, its youth ecosystem makes GPIBT the first testing ground for the governance of pastoral and economic spaces.

11

GBM Synod Pilots 2027

Four GBMs join as pilot synods in 2027, in line with RKAB 2027 (revised November 17, 2026: six programs, namely two rollouts and four pilots). Each pilot follows the same pattern: preparation and agreements (P0); a 4-day onsite Opening, seven online sessions and Visit 2 (P1); then the Launch and a recommendations report for the wave 2 rollout in 2028 (P2). The pilots test the Program 01–04 service package before it is offered to other GBMs.

SynodWork locationOpeningVisit 2LaunchRKAB Ceiling
GMIBMKotamobaguFeb 16–19Apr 26–30Jun 7–11IDR 130.73 million
GPIBJakartaApr 6–9Jun 14–18Aug 9–13IDR 147.23 million
GPIDPalu (Donggala)Apr 13–16Jun 14–18Aug 23–27IDR 138.98 million
GERMITABeo, TalaudJun 22–25Aug 30–Sep 3Oct 25–29IDR 182.96 million

At most three pilots run concurrently, in line with the limit in the RKAB: April 13–June 11 (GMIBM, GPIB and GPID) and June 22–August 27 (GPIB, GPID and GERMITA). GMIBM finishes on June 11, before GERMITA opens on June 22. The GPIB pilot starts in early April 2027 (revised November 14, 2026); because Visit 2 for GPIB and for GPID both fall on June 14–18, GPIB is accompanied by three Program Team members from Banggai Kepulauan. Each GBM's profile (number of congregations, members, network readiness and existing platforms) is filled in through the P0 assessment. The RKAB ceiling already includes a shared-cost portion of IDR 35.30 million per synod.

Budget for the six programs: a 2027 ceiling of IDR 836.13 million, or IDR 665.28 million if the host covers the Program Team's accommodation and meals. The GKLB Synod, which had been scheduled as a pilot in the November 13–14, 2026 revision, is not included in the six programs for 2027.

12

Program Governance

Governance uses the Strategic Plan structure (Steering Council, Pillar Champion, Implementation Team) with the PMO as the center of execution. Implementation decisions within each GBM remain with that synod's own leadership.

Forum / roleMembersAuthorityRhythm
Strategy Steering CouncilBPH of the General Synod, Chairs of the GPIBK & GPIBT Synods, 3–5 Synod Chairs of other GBMsDirection, priorities, budget, gate decisionsQuarterly (QPR)
Program SponsorPillar 4 Pillar ChampionAccountable for program OKRs; escalationMonthly
Program BoardProgram Sponsor, PMO, WS1–WS6 leads, GBM Project OwnersWork plan, risks, scope changesMonthly
PMO (Program Commission)Program Manager, Project Manager per GBM, analystsSchedule, resources, reporting, qualityWeekly
Design & Data AuthorityPlatform architect, GBM Data Stewards, WS1 representativeData standards, integration, access, technical changesBiweekly
Theological GateTheology CommissionApproval of formation materials and pastoral space featuresPer release
GBM Project TeamProject Owner, Data Steward, Liaison Officer, Digital AmbassadorsImplementation in synods, classes and congregations2-week sprints
Synodal Partnership CouncilBPH of the General Synod + 1 representative from each GBMJoint funding, wave 2Annual (Q4)

RACI for key decisions:

DecisionsAccountableResponsibleConsultedInformed
Passing the go-live gateGBM Synod ChairGBM Project Owner + PMODesign & Data AuthoritySteering Committee
Data and access standardsDesign & Data AuthorityWS1GBM Data StewardProgram Board
New formation materialsTheology CommissionWS4ResearchUser GBMs
Scope and budget changesProgram SponsorPMOFinancial Self-RelianceSteering Committee
Impact evaluationResearchWS6PMO, Public RelationsSteering Council, GBMs
13

Change Management and Capacity Building

The greatest risk in 2027 is not technology but training that does not turn into work habits. That is why every training is based on real tasks and followed by mentoring that is gradually tapered off.

Five GPI Academy 2027 learning tracks:

TrackParticipantsCore materialsProof of competence
Congregation Data ManagerCongregation/classis staff, Data StewardsSMJ, data dictionary, data protectionEntering and verifying the data of one column without assistance
Synod System Admin1–2 people per synodConfiguration, access, backupCreating role-based accounts; running a restore test
Digital LeadershipPastors, Elders, GBM BPMS5–7 SS02 competencies; Theology of Disruption & Digital EthicsA congregational action plan with one OKR
Digital Literacy for MembersMembers of all agesCourses T01–T16Completing a practical assignment per topic
Catechism TeachersTeachers and Council membersKatekisasi.Online Teachers' RoomRunning one stage of hybrid catechism

Change practices used:

  • Digital Ambassadors per classis: pairs of a young person and a senior minister who learn from each other; they serve as the first line of help.
  • Consistent key messages: "Strengthening fellowship, not weakening autonomy" and "Technology as the tool, our neighbor as the goal".
  • Small wins announced: one story per month from the pilot congregations on GEREJABERSAUDARA.ID and the synod portal, with permission.
  • Offline channels remain: paper forms and phone calls are still served; staff record them into the system.
  • Feedback from non-users: interviews with members who do not use the platform, every quarter.
14

Data, Security and Compliance with the PDP Law

GPIBK and GPIBT member data are already on the production platform. That makes the Data Protection Policy and the data processing agreement urgent: both must be approved before gate G1 and before expansion to other classes or congregations. For the three pilot synods, the agreement is signed before member data is used. The model is federated: each GBM is the controller of its members' data; the General Synod acts as processor and recipient of aggregates.

Data classExamplesAccessTreatment
PublicFormation materials, schedules, congregation names & locations, aggregate countsEveryoneMay be shared across GBMs
AdministrativeMember and family data, confirmation status, pastor dataBased on duties, per congregation/classisWritten consent; corrections by the Data Steward
SensitivePastoral notes, health, children's data, Ceritain storiesHighly restricted; technical admins are not automatically entitledEncryption, access logs, moderation and referral guidelines
FinancialOfferings, BakuBantu/Berkatin transactionsTreasurers and auditorsSegregation of duties; audit trail

Mandatory security baseline before go-live:

  • Personal accounts for every manager; MFA for all admins
  • Role-based access rights and account reviews every quarter
  • Daily backups and restore tests every quarter
  • Developer access limited by time and reason, recorded in the log
  • Incident response procedure: who assesses, who notifies affected members
  • Consent forms in plain language, including how to withdraw consent
  • Domains, licenses and admin access are held by the institution, not by individuals
15

Resources and Financing

The budget is approved in two stages (Q1–Q2 and Q3–Q4) so that the second stage is based on actual costs from the pilot go-live. Amounts are not yet listed because quotations and rates have not been validated.

Total cost = setup + operations + mentoring & capacity + maintenance & protection + contingency
RoleProposed numberSource
Program Manager1General Synod (PMO)
Rollout Project Manager1 per GBMPMO, may be combined
Platform & integration architect1Digital Enablement Office
Functional consultants (membership, finance)2Digital Enablement Office / partners
Training facilitators2–3Research and Development, Theology Commission, Academy
Project Owner, Data Steward, Liaison Officer3 per GBMGBM
Digital Ambassadors2 per classisGBM youth and ministers

Funding follows the Strategic Plan's "shared investment" model: the Core Operating Budget from the General Synod, the Strategic Program Budget from participating GBMs, plus sponsors, CSR and grants mapped by the Financial Self-Reliance Commission. Inter-island travel costs are kept down with a hybrid pattern: field visits only for mobilization, go-live and evaluation; everything else online through Rapat.Online.

16

Risk Register

The top three risks concern people and data, not technology; all are controlled through gates and mentoring.

RiskImpactLikelihoodMitigationOwner
Training does not become a work habit; the system is abandoned after go-liveHighHighTask-based training; 6-week hypercare; Digital Ambassadors; weekly usage metricsPMO
Inaccurate demo data carried over into productionHighMediumCouncil verification; sample audit ≥95%; focus on Minimum Pastoral DataGBM Data Steward
Leakage or misuse of personal dataHighLow–mediumGate G1 PDP policy; MFA; role-based access; access logsWS1
Weak connectivity in the islandsMediumHighMobile-first design; downloadable materials; data entry at classis pointsWS2
Dependence on one or two key peopleHighMediumOperational documentation; at least 2 admins per synod; written handoverProgram Sponsor
Stage 2 funding delayedMediumMediumStaged approval; Q2 actual cost report; backup sponsorsFinancial Self-Reliance
GBMs feel regulated rather than facilitatedHighMediumGo-live decisions in the hands of the GBM Synod Chair; "strengthening fellowship" messagingPublic Relations
Youth spaces (Ceritain, Berkatin) give rise to pastoral cases or transaction complaintsMediumMediumModeration guidelines, referrals and a complaints mechanism before wide promotionWS5
17

Decisions and the First 90 Days (November 2026 – January 2027)

The roadmap can only begin on January 4, 2027 if four BPH decisions are made no later than December 15, 2026.

  • BPH appoints the Program Sponsor (Pillar 4 Pillar Champion) and the PMO Program Manager
  • BPH approves the Project Charter for the GPIBK & GPIBT rollout, the four GBM pilots and the stage 1 budget
  • The Chairs of the GPIBK and GPIBT Synods appoint the Project Owner, Data Steward and Liaison Officer
  • The draft Digital Ministry & Data Protection Policy goes to review by the Theology Commission and legal counsel
  • PMO drafts the detailed F0–F1 plan and the January mobilization visit schedule
  • Research and Development prepares the baseline survey instruments (whitepaper Appendix B)
  • WS2 standardizes the GPIBK.CHURCH and GPIBT.CHURCH production platforms already running (module versions, backups, access rights)
  • Follow-up to the GPIBT (November 3) and GPIBK (November 5) Evaluation Meetings: Family Card Month and Contact Channel, attendance register starting on the First Sunday of Advent, reports on the 5th of every month
  • Tabletop simulation of the 48-Hour Protocol in Klasis Peling Timur (GPIBK) and MUPEL 5 Tolitoli (GPIBT) at the end of January 2027 as the starting point for KR1.4
  • Public Relations prepares a program progress page on GEREJABERSAUDARA.ID
  • Joint online program kick-off with GPIBK & GPIBT on January 8, 2027
18

Sources and Verification Notes

Content was read directly from the GEREJABERSAUDARA.ID platform database on November 1, 2026, and from the GPIBK.CHURCH and GPIBT.CHURCH production platforms on November 5, 2026.

Notes to be confirmed:

  • The Home page says "SMSA GPI 2025 (Beo, Talaud)", whereas the SMSA and Proposition pages place the SMSA in Jakarta (December 2–5, 2025) and the SSA in Beo. This roadmap uses the second version; the Home page text should be corrected.
  • The ratification status of the GPI Basic Order (KR 1.2.1 of the Strategic Plan) has not yet been found on the platform.
  • The GPIBK/GPIBT member counts are records on the production platform (entered since August 2026), not yet verified member counts.

Usage notes

This page is a working document that is still a proposal for the BPH of the General Synod of GPI, not yet an official decision. Target figures will only be locked at the Q1 2027 review once a baseline is available. The GPIBK and GPIBT member counts come from the production platforms and have not yet been verified by the Church Councils.

Project Plan & GanttQuarter I 2026 Program PropositionStrategic Plan 2025–2030Digital Ecclesiology Whitepaper